Trial runs at Mumbai’s first large-scale waste-to-energy plant in Deonar are set to begin in December 2026. Built at a cost of ₹648 crore, the Brihanmumbai Municipal Corporation (BMC) facility is currently 93% complete and is slated for full operations by early 2027, following delays due to statutory clearances, logistical hurdles, and capacity upgrades. Designed to process 600 tonnes of fresh municipal solid waste daily to generate up to 8 MW of power, the plant will undergo a one-to-two-month testing phase to evaluate its output. Once trials succeed, the BMC will seek approval from the Maharashtra Electricity Regulatory Commission (MERC) to sell the electricity.
News by Rahul Yelligetti.